26-Jun-2013 Received clearance from National Highways Authority for crossing highways for laying Coal Conveyors and Sea Water Pipelines
26-Feb-2013 Received CRZ Clearance
26-Jul-2011 Received Clearance from Railway Authorities for Crossing of Railway lines for laying Coal Conveyors and Sea Water Pipelines
18-May-2011 Received Final Environmental Clearance from MoEF
15-Dec-2010 Signing of Tripartite MoU with ICBC and CDTE for financing the project
15-Dec-2010 Issue of LoI to CDTE for 3x660 MW Supercritical Units
22-Nov-2010 Submitted application for Final EC Clearance
16-Nov-2010 Successfully completed public hearing
07-Oct-2009 In-principle clearance from Tamilnadu Maritime Board for drawal of sea water intake system
19-Jan-2009 Hitkari Fibres Limited renamed as SRM Energy Ltd.
18-Dec-2008 Power Purchase Agreement signed with Tata Power Trading Co. Ltd.
05-Dec-2008 Letter of facilitation extended for an additional 1000 MW to be setup
06-Oct-2008 NIT for ICB tender for EPC contract published. Bidding process in progress
09-Jul-2008 ToR for 3x600 MW issued by MoEF. Draft EIA/EMP report being finalized
18-Mar-2008 Change of Management from Hitkari family to Spice Energy Group
28-Dec-2007 Received Letter of facilitation for 1000 MW from Government of Tamil Nadu
|