26-Jun-2013
Received clearance from National Highways Authority for crossing highways for laying Coal Conveyors and Sea Water Pipelines

26-Feb-2013
Received CRZ Clearance

26-Jul-2011
Received Clearance from Railway Authorities for Crossing of Railway lines for laying Coal Conveyors and Sea Water Pipelines

18-May-2011
Received Final Environmental Clearance from MoEF

15-Dec-2010
Signing of Tripartite MoU with ICBC and CDTE for financing the project

15-Dec-2010
Issue of LoI to CDTE for 3x660 MW Supercritical Units

22-Nov-2010
Submitted application for Final EC Clearance

16-Nov-2010
Successfully completed public hearing

07-Oct-2009
In-principle clearance from Tamilnadu Maritime Board for drawal of sea water intake system

19-Jan-2009
Hitkari Fibres Limited renamed as SRM Energy Ltd.

18-Dec-2008
Power Purchase Agreement signed with Tata Power Trading Co. Ltd.

05-Dec-2008
Letter of facilitation extended for an additional 1000 MW to be setup

06-Oct-2008
NIT for ICB tender for EPC contract published. Bidding process in progress

09-Jul-2008
ToR for 3x600 MW issued by MoEF. Draft EIA/EMP report being finalized

18-Mar-2008
Change of Management from Hitkari family to Spice Energy Group

28-Dec-2007
Received Letter of facilitation for 1000 MW from Government of Tamil Nadu

 
Copyright © 2009. SRM Energy. All Rights Reserved